Contract Summary

Realtime civil engineering worked on the culturally significant structure of Mausoleum at Highgate Cemetery.

Due to the nature of the site Realtime carried out multiple scope items so that the construction period was as streamlined as possible. This minimised any cross over of subcontractors.

Realtime summary of work scope:

  • Enabling works package.
  • Piling (Concrete bored piles) and piling attendance. Substructure work including reinforced concrete pile caps, beams and extensive drainage.
  • Visual concrete structure superstructure with vaulted roof.
  • Bespoke falsework to the roof structure.

Contract in Brief

Principal Contractor: Craig Hamilton Architecture

Architect: Craig Hamilton Architecture

Engineer: Frank Hayward & Associates