Home>Case Studies>Maggies, Northampton

Maggies, Northampton

Contract Summary

Construction of 2m deep strip foundations and ground floor slab to include all drainage and holding down bolts to take the steel frame.

Hard and soft landscaping to include feature entrance wall, planting of trees and shrubs.

Construction of rear water feature and associated pathways.

Carparking space to rear and all line marking.

Contract in Brief

Market Sector: Health Sector

Scope of Works: Substructure Works, Hard/soft landscaping

Main Contractor: Sir Robert McAlpine

Engineer: Les Postawa Associates

Architect: Stephen Marshall Architects.

Duration: 19 weeks

Value: £619,000

Contract Start Date: July 2024