AZ SOB Enabling
Contract Summary
Installation of all foul and storm drainage site wide.
Foul water diversion to install new foul run to the external elevation of the SOB.
Installation of service corridors to North and South central zone.
Construction of MUGA and swale areas to include granite paving and landscaping.
Installation of piling platform to the SOB (South Office Building).
Installation of hard standing to the external areas of SOB for logistics during construction works.
Contract in Brief
Market Sector: Commercial
Scope of Works: Enabling Works
Main Contractor: MACE Ltd
Engineer: Arups
Architect: TBC
Duration: 32 weeks
Value: £5m
Contract Start Date: July 2024