Contract in Brief

Market sector
Commercial

Scope of works
Basement Works

Main contractor
Sir Robert McAlpine Ltd

Engineer
Conisbee

Architect
BDP

Duration
80 weeks

Value
£6.3m

Contract start date
May 2017

Contract summary

Salvage of hard landscaping materials, limited demolition & alterations (of RC and Brickwork elements), groundworks including steel sheet piling, underpinning, reduce level dig and installation of temporary propping.

Construction of a three storey underground concrete frame including all waterproofing & drainage systems. Reinstatement of existing hard landscaping. Including macadam, York-stone paving and granite setts.

SHORTLISTED FOR "CONSTRUCT" CONCRETE STRUCTURES GROUP AWARD FOR PROJECTS OVER £2.5M