...laying the foundations for the future

GSK Ware – Hertfordshire

GSK Ware – Hertfordshire

Contract in Brief

Market sector
Commercial

Scope of works
Substructure & Superstructure

Main contractor
MACE

Engineer
Ross & Partners

Architect
Simons

Duration
26 weeks

Value
£1.95m

Contract start date
February 2014

Contract summary

Works associated with reducing levels, forming mass concrete pad foundations, Drainage, Ground Floor slab and concrete topping to hollow rib decking on upper floors. Works also involved forming of a watertight concrete underpass, including associated temporary works.