Contract in Brief

Market sector
Commercial Residential

Scope of works
Substructure & Superstructure

Main contractor
Sir Robert McAlpine

Engineer
Ramboll UK

Architect
Squire & Partners

Duration
38 weeks

Value
£1.5m

Contract start date
January 2014

Contract summary

Regeneration and new build development of a grade ll listed building in Mayfair London

Works included Bulk excavation, temporary works, underpinning, RC basement construction, waterproofing, underground drainage, services, RC frame4, RC stairs and concrete to metal decking.